4. Call Setup
When the link is configured as a Permanent Virtual Circuit (PVC), support for Switched Virtual Circuit (SVC) call setup and clearing is not required. Calls are Established and Terminated using PPP LCP packets.
When the link is configured as a Switched Virtual Circuit (SVC), the first octet in the Call User Data (CUD) Field (the first data octet in the Call Request packet) is used for protocol demultiplexing, in accordance with the Subsequent Protocol Identifier (SPI) in ISO/IEC TR 9577 [5]. This field contains a one octet Network Layer Protocol Identifier (NLPID), which identifies the encapsulation in use over the X.25 virtual circuit. The CUD field MAY contain more than one octet of information.
The PPP encapsulation MUST be indicated by the PPP NLPID value (CF hex). Any subsequent octet in this CUD is extraneous and MUST be ignored.
Multipoint networks (or multicast groups) MUST refuse calls which indicate the PPP NLPID in the CUD.
The accidental connection of a link to feed a multipoint network (or multicast group) SHOULD result in a misconfiguration indication. This can be detected by multiple responses to the LCP Configure-Request with the same Identifier, coming from different framing addresses. Some implementations might be physically unable to either log or report such information.
Conformance with this specification requires that the PPP NLPID (CF) be supported. In addition, conformance with [4] requires that the IP NLPID (CC) be supported, and does not require that other NLPID values be supported, such as Zero (00), SNAP (80), CLNP (81) or ES-IS (82).
When IP address negotiation and/or VJ header compression are desired, the PPP call setup SHOULD be attempted first. If the PPP call setup fails, the normal IP call setup MUST be used.
The PPP NLPID value SHOULD NOT be used to demultiplex circuits which use the Zero NLPID in call setup, as described in [4]. When such a circuit exists concurrently with PPP encapsulated circuits, only network layer traffic which has not been negotiated by the associated NCP is sent over the Zero NLPID circuit.
Rationale
Using call setup to determine if PPP is supported should be inexpensive, when users aren't charged for failed calls.
Using the Zero NLPID call together with PPP could be expensive, when users are charged per packet or for connect time, due to the probing of PPP configuration packets at each call.
PPP configuration provides a direct indication of the availability of service, and on that basis is preferred over the Zero NLPID technique, which can result in "black-holes".