2. Installation of communcation gear 8/1/69

2a. From AT&T and/or BBN need dimensional, power and cabling specifications​

2b. Need to establish SRI desired alternate locations so as to determine maximum telco cable lengths​

2c. Need to establish location and drops on voice coordination circuits​

2d. Need circuit information on voice drops for tie to intercom system​

2e. Need to order and install a.c. power (coordinate with 4b)​

2f. See 16​