Skip to main content

2. Physical Layer Requirements

PPP is capable of operating across most DTE/DCE interfaces (such as, EIA RS-232-C, EIA RS-422, EIA RS-423 and CCITT V.35). The only absolute requirement imposed by PPP is the provision of a full-duplex circuit, either dedicated or circuit-switched, which can operate in either an asynchronous (start/stop), bit-synchronous, or octet-synchronous mode, transparent to PPP Data Link Layer frames.

Interface Format

PPP presents an octet interface to the physical layer. There is

no provision for sub-octets to be supplied or accepted.

PPP does not impose any restrictions regarding transmission rate, other than that of the particular DTE/DCE interface.

Control Signals

PPP does not require the use of control signals, such as Request To Send (RTS), Clear To Send (CTS), Data Carrier Detect (DCD), and Data Terminal Ready (DTR).

When available, using such signals can allow greater functionality and performance. In particular, such signals SHOULD be used to signal the Up and Down events in the LCP Option Negotiation Automaton [1]. When such signals are not available, the implementation MUST signal the Up event to LCP upon initialization, and SHOULD NOT signal the Down event.

Because signalling is not required, the physical layer MAY be decoupled from the data link layer, hiding the transient details of the physical transport. This has implications for mobility in cellular radio networks, and other rapidly switching links.

When moving from cell to cell within the same zone, an implementation MAY choose to treat the entire zone as a single link, even though transmission is switched among several frequencies. The link is considered to be with the central control unit for the zone, rather than the individual cell transceivers. However, the link SHOULD re-establish its configuration whenever the link is switched to a different administration.

Due to the bursty nature of data traffic, some implementations have choosen to disconnect the physical layer during periods of inactivity, and reconnect when traffic resumes, without informing the data link layer. Robust implementations should avoid using this trick over-zealously, since the price for decreased setup latency is decreased security. Implementations SHOULD signal the Down event whenever "significant time" has elapsed since the link was disconnected. The value for "significant time" is a matter of considerable debate, and is based on the tariffs, call setup times, and security concerns of the installation.